Hello,

 

Is it possible to modify the activity ID when receiving a PO.

 

Thank you for your help.

 

Christophe.

 

 

Best answer by Abdul

Hi ​@DMTCCAN,

No, it is not possible to change the Project information while receiving the Purchase Order. 

Please change at the Purchase Order level before registering the arrival.

 

Regards

Abdul Rehman

View original

3 replies

Abdul
Superhero (Partner)
Forum|alt.badge.img+20
  • Superhero (Partner)
  • Answer
  • May 22, 2025 10:23 AM UTC

Hi ​@DMTCCAN,

No, it is not possible to change the Project information while receiving the Purchase Order. 

Please change at the Purchase Order level before registering the arrival.

 

Regards

Abdul Rehman


DMTCCAN
Sidekick (Customer)
Forum|alt.badge.img+6
  • Author
  • Sidekick (Customer)
  • May 22, 2025 10:28 AM UTC

Thank you Abdul !

 

Do you mean that the user has to go back to the PO screen and change at this level !

 

Regards

 

Christophe.

 

 


Abdul
Superhero (Partner)
Forum|alt.badge.img+20
  • Superhero (Partner)
  • May 22, 2025 10:37 AM UTC

​@DMTCCAN, Yes, the user needs to go back to the PO screen to update the Project connection.