Hello,

 

Is it possible to modify the activity ID when receiving a PO.

 

Thank you for your help.

 

Christophe.

 

 

Hi ​@DMTCCAN,

No, it is not possible to change the Project information while receiving the Purchase Order. 

Please change at the Purchase Order level before registering the arrival.

 

Regards

Abdul Rehman


Thank you Abdul !

 

Do you mean that the user has to go back to the PO screen and change at this level !

 

Regards

 

Christophe.

 

 


@DMTCCAN, Yes, the user needs to go back to the PO screen to update the Project connection.