Hi! 

I use IFS8. Buyers meet this kind of problem almost once per month. The PO need 2 user’s approval. The buyer released a PO. The first one approved it. Then the PO status changed to Planned. The second one can not approve it. Buyer had to release this PO again and the first one approve it again also. Then the second one can see and approve this PO.

Is there someone else have this kind of problem? Is it a bug? Or something happened buy I don’t know.

 

 

icon

Best answer by AsankaGaru 27 January 2022, 19:20

View original

This topic has been closed for comments

2 replies

Userlevel 6
Badge +11

Hi,

PO state is anyway staying in ‘Planned’ when an authorization is pending. Its just the ‘authorization required’ checkbox is marked.

Do you mean ‘authorization required’ checkbox is getting cleared when the first user authorize?

 

Userlevel 4
Badge +10

@AsankaGaru

Hi!

You are right.  The ‘authorization required’ checkbox is getting cleared when the first user authorize. Then it need authorize from the first lever again.