Hello,

With PO dates in IFS, the system prioritizes older POs first and newer ones later. When we cut a new PO to replace an MRB'd part, IFS assigns the new PO a target date at the end of the sequence and pulls in the older POs instead.

Is there a setting that can disable this behavior? It creates a lot of noise, especially during allocations or when managing MRBs.

We’re currently using IFS Apps 10. I have reviewed available settings everywhere I can think of (Site, Purchase Part, PO, Basic Data, etc.).