Question

Order proposal - Time period for material on work orders

  • July 29, 2026
  • 1 reply
  • 16 views

Forum|alt.badge.img+2

Hi.
When I use Create Order Proposal… Materials on a work task with required date = today is generating a need (a Purchase Requisition is created).
But when required date > today, no Purchase Requisition is created.

I want to extend the horizon the Create Order Proposal looks to include material need on work tasks within the next 30 days.

 

We are a service company and only need material for work orders.
We have a warehouse where we stock the most parts.
We do not have the IPR module.

IFS Cloud 25R1

How can I extend the order proposal horizon to ensure enough stock to cover work orders for lets say 30 days?

1 reply

Forum|alt.badge.img+12

Hi ​@ModinA, do you have a Purchase Lead Time for your part? Order Proposal will only check the supplies within one lead time. If there are enough supplies within one lead time to refill stocks up to the order point, then no new supplies (PRs) will be created. Thanks.