Skip to main content
Question

Order proposal - Time period for material on work orders

  • July 29, 2026
  • 0 replies
  • 1 view

Forum|alt.badge.img+2

Hi.
When I use Create Order Proposal… Materials on a work task with required date = today is generating a need (a Purchase Requisition is created).
But when required date > today, no Purchase Requisition is created.

I want to extend the horizon the Create Order Proposal looks to include material need on work tasks within the next 30 days.

 

We are a service company and only need material for work orders.
We have a warehouse where we stock the most parts.
We do not have the IPR module.

IFS Cloud 25R1

How can I extend the order proposal horizon to ensure enough stock to cover work orders for lets say 30 days?