Hi, Is it possible to set the MRP parameters to only look so far ahead? At the moment, as soon as a req is created (even if for next year), MRP suggests buying or making the stock. I do not want to consider that order until at 3 months prior to required date. It would be ideal to see demand without any req’s being generated. Using planning method G currently.