We are using Supplier Schedule a lot in Procurement, and this MRP message makes our Supply Chain more work. This message is generated when the Due date of MRP Buy Quantity falls before supplier schedule's valid from date (when MRP run).
For below case, the 16pcs is not showing on the Supplier Schedule. Currently, we are manually putting it into PO.O-p
I want to ask, if it’s possible to have the valid from date in the past? We want display the Past Due requirement without manually doing anything.