We have an issue with purchase requisitions where MRP does not consider available qty on other site. We have 2 sites in a company, Let’s say A and B. A is a material-supply site, B is a manufacturing site. So when MRP runs for site A, it does not take qty on site B in the calculation, this generates a lot of mess for us. Please help and thanks in advance
Page 1 / 1
Hi,
It sounds as if multi-site BOM’s will help you?
I have attached a short presentation covering this so hopefully will help.
Regards,
Antony