Question

MRP Background job

  • 27 October 2021
  • 1 reply
  • 109 views

Userlevel 3
Badge +6

Hi All,

 

Below is the error I am getting in Background Job.

Any idea?

 

‘Error snapshot MRP Supply/Demand. MRP can not find required date of Order No

40108293 for Site/Part/ABC Class BCN/02200069821-C in calendar DIST’


This topic has been closed for comments

1 reply

Userlevel 7

Hi All,

 

Below is the error I am getting in Background Job.

Any idea?

 

‘Error snapshot MRP Supply/Demand. MRP can not find required date of Order No

40108293 for Site/Part/ABC Class BCN/02200069821-C in calendar DIST’

You Work Time Calendar “DIST” has an end date that is before the required date on the order. 
 

Extend the calendar (change the end date) and then regenerate the calendar.
 

 