‘Error snapshot MRP Supply/Demand. MRP can not find required date of Order No

40108293 for Site/Part/ABC Class BCN/02200069821-C in calendar DIST’

Hi All,

 

Below is the error I am getting in Background Job.

Any idea?

 

‘Error snapshot MRP Supply/Demand. MRP can not find required date of Order No

40108293 for Site/Part/ABC Class BCN/02200069821-C in calendar DIST’

You Work Time Calendar “DIST” has an end date that is before the required date on the order. 
 

Extend the calendar (change the end date) and then regenerate the calendar.
 

 