Hi All,
Below is the error I am getting in Background Job. Any idea?
‘Error snapshot MRP Supply/Demand. MRP can not find required date of Order No 40108293 for Site/Part/ABC Class BCN/02200069821-C in calendar DIST’ |
Page 1 / 1
Hi All,
Below is the error I am getting in Background Job. Any idea?
‘Error snapshot MRP Supply/Demand. MRP can not find required date of Order No 40108293 for Site/Part/ABC Class BCN/02200069821-C in calendar DIST’ |
You Work Time Calendar “DIST” has an end date that is before the required date on the order.
Extend the calendar (change the end date) and then regenerate the calendar.
If you are using IEE, the options would be found by using RMB.
Enter your E-mail address. We'll send you an e-mail with instructions to reset your password.