Why these TT lines are showing up in the order proposals?

 

It doesn’t make sense. They are already here and reserved, why would the system think we need more.

 

 

If a transport task line has reserved stock with the purpose of moving that stock away to another site, then it needs to act as any other demand that causes a decrease of plannable stock on the site. If the transport task is moving stock within the same site then the transport task line will act as both supply and demand so that the balance will be zero and not extra supply will be generated.