Insufficient Privileges for Project connected POCO authorization

  • January 15, 2025
  • 1 reply
  • 38 views

Asela Munasinghe
Superhero (Customer)
Forum|alt.badge.img+23

Hi All

One of our project Directors tries to authorize a POCO which was changed to a negative delta amount and he's getting the the error Insufficient privileges error message. This is how the applicable rule looks like:

 


He previously succesfully authorized the PO, now only getting the error in POCO. 

What could be the reason? This is 24.1.1

Best answer by Asela Munasinghe

This turns out to be a permisison issue, nothing related to the Purchase Authorization Rule. 

Granted the Projection PurchaseOrderChangeOrderHandling to the relavant permission set the user has, now it works for him. Issue solved! 

View original
Did this topic help you find an answer to your question?

1 reply

Asela Munasinghe
Superhero (Customer)
Forum|alt.badge.img+23
  • Author
  • Superhero (Customer)
  • 743 replies
  • Answer
  • January 17, 2025

This turns out to be a permisison issue, nothing related to the Purchase Authorization Rule. 

Granted the Projection PurchaseOrderChangeOrderHandling to the relavant permission set the user has, now it works for him. Issue solved! 