How do we handle Milestone based payment in Sub Contracts?

How do we handle Milestone based payment in Sub Contracts?

Can Sub Contract Valuation Plan be used to create payment based on the completed work?


How do we handle Milestone based payment in Sub Contracts?

Can Sub Contract Valuation Plan be used to create payment based on the completed work?

Hi ​@FPayab,

 

The Sub Contract Valuation is exactly used for this purpose.

You can create Manual Supplier Invoices for each Valaution and make Payments.


How do we handle Milestone based payment in Sub Contracts?

Can Sub Contract Valuation Plan be used to create payment based on the completed work?

Hi ​@FPayab,

 

The Sub Contract Valuation is exactly used for this purpose.

You can create Manual Supplier Invoices for each Valaution and make Payments.

Does this also mean that i can create a partial valuation for (example) 5 quantity from the total of 10 qty for the same Line/item when using Quantity Valuation Method?