how do i Chang the activity of a PR/PO

  • November 11, 2022
  • 1 reply
  • 42 views

Forum|alt.badge.img+4

Is there any way to chnage the PR/PO activity connection in case someone made a mistake in connection the line to the wrong actitivity in the Project Itmen Navigator ? The downside is that it also taking over the planned dates wich is causing troubles.

(using IFS 9)

1 reply

Forum|alt.badge.img+17
  • Superhero (Employee)
  • September 6, 2023

Hi,

I’m not sure if I understood you properly, but you can change activity connection from the PR/PO line with the RMB option ‘Project Connection’ → ‘Connect to Activity’.

Regards,

Pilar