Is there any way to chnage the PR/PO activity connection in case someone made a mistake in connection the line to the wrong actitivity in the Project Itmen Navigator ? The downside is that it also taking over the planned dates wich is causing troubles.

(using IFS 9)

Hi,

I’m not sure if I understood you properly, but you can change activity connection from the PR/PO line with the RMB option ‘Project Connection’ → ‘Connect to Activity’.

Regards,

Pilar