Hello,
Are you able to disconnect a PO from one activity and connect it to another activity within a project? We would close the PO and create a new one but the PO has already been sent to the supplier.
Best answer by Susith Setunga
View originalHello,
Are you able to disconnect a PO from one activity and connect it to another activity within a project? We would close the PO and create a new one but the PO has already been sent to the supplier.
Best answer by Susith Setunga
View originalHi Naren,
There is no direct disconnecting method as the demand has already created a PO. However this is possible with the following workaround steps.
This may not be the ideal solution but I hope you can work around with this. Please check and let me know if that works.
Regards
Susith
Susith - brilliant! Now why didn't I think of that :-)?
I will try it and let you know. Thanks a million.