We are in the process of upgrading IFS 8 to IFS 10 UPD13. A demand Planner is installed in a server and configured for the new IFS 10 environment.

While running ‘Create Forecast’, we are getting the error ‘The Period has already been aggregated. Create Forecast can only be ran once per period". It started giving the error from the first run itself and no forecast is getting created.

  • The flow SQL are checked and found to be in order with the APPOWNER prefix.
  • Period are checked and are in order.
  • Based on other suggestions, we tried to check the registry entry (‘FixedDate’), but we could not find any registry entry available in the registry path ‘HKEY_LOCAL_MACHINE\SOFTWARE\IFS\ForecastServer\5.0\Settings’ in Demand server.

 

Not sure what are we missing. Any help on this is appreciated.

Thanks a lot.

 

Best Regards,

 

Siva Ganesh M

 


2 replies

Userlevel 3
Badge +7

We are having this issue as well. We had the issue during testing but were told it would “likely work” when we go live with Apps 10. Here we are now needing to run a forecast and are getting the same error. It seems like no one has an answer for this. We checked the same things as you as well.

Userlevel 5
Badge +12

See the answer in this related post;

 