Customer Schedule Forecast

  • January 20, 2021
  • 1 reply
  • 529 views

ctaylor56
Hero (Partner)
Forum|alt.badge.img+14

Question, if you’re receiving customer schedule forecasts from Customers but they are for parts that are not Master Scheduled, where does that schedule go after releasing the schedule.  I see the Demand Line in Inventory Part Availability Planning with a status Planned.  But how do I clear that?  MRP is planning for this.  Typically when I import that into Master Scheduling, I no longer see the demand type of Customer Schedule Forecast, but for this case where I am not MS’ing this part, how do I clear that?

Best answer by ctaylor56

Line Type of Informational Only should achieve this since Delivery Not Authorized and Delivery Authorized are considered by MRP.

This topic has been closed for replies.

1 reply

ctaylor56
Hero (Partner)
Forum|alt.badge.img+14
  • Author
  • Hero (Partner)
  • Answer
  • February 8, 2021

Line Type of Informational Only should achieve this since Delivery Not Authorized and Delivery Authorized are considered by MRP.