Hi Experts.

We have this requirement to capture engineer start and end times of Time registrations.

 

Example: Here in MWO they enter start and Stop time so the hours is captured.

 

But in the Cloud we could not see these start and Stop times instead the Hours only??

 

 

 

We need to produce a Report to the HR with these Start and End times so that they can analyze Productivity with engineer time reporting pattern, so where in the application we can get these data?

 

Following is an Exmple from another system you can see From and To time as well,,what we are after.

 

 

 

Kind Regards

KM

Best answer by PLabor

In Apps10, we use the Work Task Clocking screen to pull this information easily and repeatedly.  

3 replies

Forum|alt.badge.img+8
  • Author
  • Sidekick (Partner)
  • June 3, 2025

Note:

I can see that this View contains data i.e. JT_TASK_CLOCKING so I can get a Quick Report may be but looking for a standard screen to see these information so I can easily export the selection


Forum|alt.badge.img+7
  • Sidekick (Customer)
  • Answer
  • June 3, 2025

In Apps10, we use the Work Task Clocking screen to pull this information easily and repeatedly.  


Forum|alt.badge.img+4
  • Do Gooder (Partner)
  • June 3, 2025

Work assignment