Work Task Postings overwritten

  • December 17, 2025
  • 2 replies
  • 59 views

HAFFRASVE
Sidekick (Customer)
Forum|alt.badge.img+8

We have recently upgraded from 24R1 to 25R1 and noticed an unexpected behaviour related to pre-postings.

Our WO have 2 code parts 

While we get the 3 other code parts from the object. 

Quite often users change the code parts for some of the tasks in the WO (other purpose and financial project)

We have now noticed that when others later add a priority or updates the task with additional long description on the task the pre-postings are changed back to the values from the WO...

 

 

This is causing a lot of frustration or us for the moment.

Does anyone know if there is a system parameter we can change to avoid this behavior?

Best answer by Thommy

Hi ​@Frank Sveen, there is no change in the logic. This is a defect and was resently reported in the 25R1 track. A correction has been made and are available in the upcoming 26R1 release.

2 replies

HAFFRASVE
Sidekick (Customer)
Forum|alt.badge.img+8
  • Author
  • Sidekick (Customer)
  • December 17, 2025

@Thommy are you aware of any changes in pre-posting logic for work tasks between 24R1 and 25R1?  


Thommy
Hero (Employee)
Forum|alt.badge.img+12
  • Hero (Employee)
  • Answer
  • December 17, 2025

Hi ​@Frank Sveen, there is no change in the logic. This is a defect and was resently reported in the 25R1 track. A correction has been made and are available in the upcoming 26R1 release.