Question

Work Task allows to add Resource Demand even in Status Work Done but not change the status to started

  • 10 November 2023
  • 2 replies
  • 37 views

Userlevel 1
Badge +5

If the Status of the Work Task is Work Done, it allows to add Resource Demand, if it allows to add the Resource demand then the Work Task status still remains in Work Done.

is this is the functionality or any set up needed for this status change automatically.

Its in 23R1


2 replies

Userlevel 7
Badge +30

I don't know the answer to your question but perhaps the status can be changed back using a custom event or workflow?

Userlevel 5
Badge +12

This is the functionality and there is no setting to alter this behavior.

Either the user should revert the status manually to Work Started if he/she realize that more work needs to be done (= new resource demand is needed) or as Mathias suggests a custom event or workflow could be used to change the status.

 

Reply