In 25R1, we are attempting to incorporate Public Holidays into the planning allocations for Work Tasks.
We have created the Schedule Exceptions and linked them to a Calendar.
The same Calendar has also been linked to both the Site and the Resource Individual.
However, within the Resource Monitoring Gantt, the Public Holiday is still not being recognised.
Notice how the Saturday and Sunday is treated as a non-working day, we want the same for Public Holidays.