Hi Experts,
I have encountered an inconsistency with the cost per hour calculation in the Costs tab.
-
A resource group has been set up with a general cost of 50.

-
The related Maint organization is having a cost rate.

-
A Work Task (WT) was created and connected to this resource group.
-
The task was then assigned to a user, time was reported, and the work was completed.
However, we noticed that the Costs tab displays a different hourly rate than the expected value of 50. The Resource and Planning tabs reflect the correct hourly cost of 50 for the resource.



Further testing was done by executing another WT using the same resource, but the Costs tab again showed a different cost per hour.

-
How is the per unit cost in the Costs tab being calculated?
-
What could cause this discrepancy?
-
What steps can be taken to ensure the actual cost per hour (50) is correctly reflected in the Costs tab?
-
Are there any configurations or adjustments needed in Time Types or other related settings?
I would appreciate your guidance on resolving this issue.
Thank you!