Skip to main content
Solved

The date interval cannot be smaller than plan hours

  • May 29, 2023
  • 2 replies
  • 69 views

Forum|alt.badge.img+8

Hi everyone, getting this error on a recurring basis on the PM actions condition tab, while modifying the start value. and in another case while changing the status of the work task. 

any suggestion please.

 

 

Best answer by Dilini Arandara

Hi,

 

In which UPD level are you currently at? There is a correction done in UPD9 for the same error.

Bug ID: 153676

If you are in a lower UPD version, then this correction would be the solution.

2 replies

Dilini Arandara
Superhero (Employee)
Forum|alt.badge.img+12
  • Superhero (Employee)
  • Answer
  • May 29, 2023

Hi,

 

In which UPD level are you currently at? There is a correction done in UPD9 for the same error.

Bug ID: 153676

If you are in a lower UPD version, then this correction would be the solution.


Forum|alt.badge.img+8
  • Author
  • Sidekick (Partner)
  • June 7, 2023

thanks Dilini :-)