I have a customer, who configured PM Actions with ‘Performed Date Based’ option, and wants to schedule the Maintenance Plan lines through Maintenance Planning Board.

The Maintenance Plan Lines are scheduled through the MPB and generate the Work Order for the first line and execute. When the Work Order is completed, the succeeding Maintenance Plan Lines in the PM Action will be regenerated and the lines revert to ‘Needs Rescheduling‘ status.  

With this, the customer not able to use the MPB for the PM Actions. Any Idea how other customers are doing scheduling with these type of data setups.