Recreate Cancelled PM Work Requests

  • March 17, 2026
  • 1 reply
  • 9 views

Forum|alt.badge.img+10

We are in IFS 10 UPD 9.

Our Maintenance supervisor added PM Group IDs to all of his PM actions thinking he could use it for sorting.  However, this grouped all of his PM actions into 2 work requests (as designed).

He then removed all of the PM Group IDs and attempted Calendar Generation again.

The result is the Work Request was cancelled, but no new PMs were created for the month.

 

Is there a way to create the PMs for the month?

 

1 reply

Forum|alt.badge.img
  • Do Gooder (Customer)
  • March 18, 2026

Canceled maintenance plan line, does not mean that this line can be generated again. It means that this time this work was not needed. 
I would say that you either need to generate jobs manually from the PM Action or create a new revision with a new start date, so that you will be getting a new planned line for the intendent week - and then run the calendar generation.

/Christian