PM Work Order Latest Finish Date

  • November 8, 2019
  • 2 replies
  • 412 views

ctaylor56
Hero (Partner)
Forum|alt.badge.img+14

When a Calendar Generated PM Action generates a Work Order, how does IFS calculate the latest finish date?  What is the IFS logic?

Best answer by anmise

ctaylor56 wrote:

When a Calendar Generated PM Action generates a Work Order, how does IFS calculate the latest finish date?  What is the IFS logic?

I believe all it does is take the last working day of the planned week in maintenance plan and sets it as the latest finish date. If you set a last finish date on the maintenance plan line manually, it will be set on the work order, but from my testing it doesn’t seem to transfer across to the work task itself. @JerryB any input here?

View original
Did this topic help you find an answer to your question?

2 replies

  • Superhero (Employee)
  • 1439 replies
  • Answer
  • November 9, 2019
ctaylor56 wrote:

When a Calendar Generated PM Action generates a Work Order, how does IFS calculate the latest finish date?  What is the IFS logic?

I believe all it does is take the last working day of the planned week in maintenance plan and sets it as the latest finish date. If you set a last finish date on the maintenance plan line manually, it will be set on the work order, but from my testing it doesn’t seem to transfer across to the work task itself. @JerryB any input here?


ctaylor56
Hero (Partner)
Forum|alt.badge.img+14
  • Author
  • Hero (Partner)
  • 163 replies
  • November 9, 2019

Thank you