Question

PM Action for night shift 22-06

  • 17 February 2022
  • 3 replies
  • 196 views

Userlevel 3
Badge +7

I am trying to create a PM Action that would generate daily recurring work request for a night shift that works 22-06, start of generated work task should be at 22. The problem appears to be date change in midnight.

In date type “From Time” must be bigger than “To Time” thus has to define separately rows for 22:00-23:59 and 00-06. The one minute gap is needed as otherwise the “Latest Finish must be later than Earliest Start” is raised already in PM Action.

 

Unfrortunately the work request generation sets the start time at 00, not 22. The day type in calendar that I use is as below. 

 

Any good ideas how to generate work requests that start at a certain time and have the earliest-latest span through the work “day” that starts in different date than it ends?


This topic has been closed for comments

3 replies

Userlevel 2
Badge +6

Hi @Timo Tiihonen ,

Have you found a way to generate work requests under the mentioned conditions or is the issue still recurring?

BR,

Supun.

Userlevel 2
Badge +5

Possible solutin/work around to PM Action for nigth shift when action should be generated from start of shift.

 

Userlevel 2
Badge +5

For the Resource Planning (Gantt’s) you can using the following calendar set up if not HR is uded: