Question

How to undo changes made manually to the schedules in Maintenance Planning Board

  • 21 April 2022
  • 1 reply
  • 105 views

Userlevel 2
Badge +5

Hi,

Maintenance Planners usually make changes for the work order schedule after executing the automatic scheduling in Maintenance Planning Board (MPB).

Eg: Planner changes the planned start date of the work task by manually dragging and dropping the Work Task to a future date.

Is there an option in the MPB to reverse/undo the above change without manually dragging and dropping it to the date where it was earlier?

 

Thank you.

 


1 reply

Userlevel 4
Badge +8

Hi Thilochana,

I checked the functionality and manually you can change the date by drag and drop, other than that the only way I noted is you can change the planned dates in work tasks in IEE for earlier date, that you want and load MPB only for New and Modified work orders and select specific work task and do the scheduling.

If you set up dates without fixed start date, and when you do the scheduling, it picked planned dates into the latest date based on the criteria ‘as soon as possible’ despite the dates we applied. Hope this answer will help you to some extent.

Reply