Solved

Flexible WO generation - Condition Based

  • 20 October 2023
  • 2 replies
  • 52 views

Badge +3
  • Do Gooder (Customer)
  • 6 replies

We have a situation where we use condition-based PM actions to generate WOs for objects based on run hours.   
For example, let’s say the condition is set up as below.

 


So, the maintenance plan is predicted and generated as below.  All good. 
 

Practically, these objects are not getting serviced when the exact value reached.  So, the actual value or run hours on the work task performed date can be lower or higher. 
Let’s assume that we perform the maintenance at 175 hours.  So ideally the next WO generation should happen 375 hours.  But the system waits till 400 hours for automatic generation.   We can track the actual performed value using generated value and last value fields, but the automatic generation does not consider the actual performed value. No changed to the planned value. 
Is there any option in IFS to have this catered? 
 

icon

Best answer by dhwe 23 October 2023, 08:49

View original

2 replies

Badge +3

Hi,

Isn’t the “Performed Value Based” option on the Condition , together with the “Last measurement at maintenance” option working for this situation?

BR.

 

Badge +3

@dhwe  Yes and thanks Dharshana.  

Reply