Equipment downtime can be entered while the status of the Work task is updated to Work done by enabling the downtime per work type category. However it will not be allowed to modify the data once saved. How the typo errors/wrong information can be corrected?
Solved
Equipment downtime correction (Work Task)

Best answer by Thilini Kumarasinghe
Hi
I checked this functionality, and it seems no edit option is available. I tried to re-launch the downtime dialog by changing the work task status back to work started and again to work done, to do the changes, but it did not pop up at the 2nd time.
Best Regards,
Thilini