Skip to main content
Question

Due date is way long in past in the running plan

  • October 23, 2024
  • 4 replies
  • 38 views

Forum|alt.badge.img+8

Hi Everyone,
I noticed that the line generated yr plan shows a due date that has already passed(year 2021). What do you think could have led to this situation? Any insights on the possible reasons would be helpful!

this is set to value based yes. 
 

Thanks in advance

4 replies

Thilini Kumarasinghe
Ultimate Hero (Employee)
Forum|alt.badge.img+21

Hi @Hashmit 

It is difficult to identify the reason just by looking at this screen print.

Can you kindly add a screen print, displaying the values in below columns too?

 

Best Regards,

Thilini


Forum|alt.badge.img+8
  • Author
  • Sidekick (Partner)
  • October 24, 2024

HI @Thilini Kumarasinghe , THANKS for the response

I think these details should help.

 


Forum|alt.badge.img+8
  • Author
  • Sidekick (Partner)
  • October 24, 2024

 


Thilini Kumarasinghe
Ultimate Hero (Employee)
Forum|alt.badge.img+21

Hi @Hashmit 

Sorry, I cannot really figure out from this information. May be you can add the condition criteria as well , to check whether it helps ?

And also, can you add the steps the user performed, to encounter such planning data ? Is it repeatable ?

Thanks and Best Regards,

Thilini