I have an EAM project. I need to know if the dispatch console can work with Services.

I can see the work tasks in the console, but I can't see the resources.

What configuration should I have to achieve this?

I can configure the configuration in FSM, but I can't access the resources in EAM.

 

 

Hi,

 

Did you create scheduling datasets and connect them?


Hello, thank you.

Yes, I've generated the connection, the dataset, and the resource connected to the dataset.

I'll send the views.

Regards.

 

 

 

 

 


Hi ​@Miguel Alejos ,

You will see resources in DC once you run Generate Schedules and Capacity for resources from resource detail page. You can run it either for a resource structure or for a resource group or for an individual resource.
Make sure to refresh DC window as well.

Thanks,
Nethmini


I think it's a problem with my environment, I have another environment that works by doing the same steps.

Hi ​@Miguel Alejos , 

May be the issue here is with the Employee record. As the HR schedule is used employee should have a valid HR schedule defined under employee file.

Thanks,

Nethmini


The problem was the type of time in the calendar, it was solved, thanks to everyone.