Default Sales part impact on Labor line invoice for a Work Task

  • September 21, 2026
  • 1 reply
  • 11 views

Step 01

Add a default sales part to a Resource Group

Now add the above resource group as a demand to a work task and manually add a different sales part from the default sales part defined above. Do the time reporting and authorization 
 

Now check the planning line and observe the manually entered sales part is successfully shown as expected.

But when Sales Tab is checked manually entered sales part is replaced by the default sales part defined under Resource Details.

Is this the expected behavior? In that case it is not possible to manually enter sales part and do invoicing when default sale part is defined against a resource

1 reply

Forum|alt.badge.img+4
  • Do Gooder (Employee)
  • September 23, 2026

Hi ​@AshanHal,

I just tested this, and it seems to be working as it should in the latest version. The sales part I changed to on the resource demand was reflected on the sales line when I reported time against that demand. Did you report time against the demand? If you did, I think this looks strange. Which version are you on?

 

Thanks,

Daniel