Hi all maintenance expert.

My customer has a PM action triggered by condition (500h cumulative).

Let’s say that any measurement had been done for a long time and the last value measured is 1600h (Delta).

How to avoid creating all the WO (500h, 1000h, 1500h) that had been bypassed and create only the last one? 

All tips and ideas are welcome.

 

Warmest regards

 

 

 

1 reply

Priyanka Kurukuladithya
Do Gooder (Employee)
Forum|alt.badge.img+4

One option is to change the start value of the condition trigger to a value closer to the new measurement.

Another option may be to change the valid from date of the PM action. 

Both the above will remove the previous lines in the maintenance plan. But the calculation will take the old measurements if they are in the last five measurements.

If you want to ignore the old measurements and only consider the new measurements after some date for the maintenance plan calculation then you can set “Calculation Start Date” in the Equipment Object/parameters.

 