Hi,

 

I saw a new enhancement in the 25R1 release document regarding connecting work tasks to project activities rather than at work order level. However, I have tested this out and it does not appear in the work task screen. Have I missed anything?

 

Thanks,

George.

1 reply

Thilini Kumarasinghe
Ultimate Hero (Employee)
Forum|alt.badge.img+21

Hi ​@GeorgeArmstrong 

From Work order side, if you check it, there is not much change. Still the “Project Connection” option lies in the Work order level and once you connect the work order to a project, work task will also get connected to the same project activity. Activity ID, Description and Sequence can be found in the Work task level.

However, the level of detail has increased by moving the connection down to the work task level.

Object connections related to the work task are now displayed on a sub level to the work task connection increasing the visibility.

 

24R2:

25R1:

 

 

Best Regards,