Question

Condition Based PM Plan Out Of Sync

  • July 29, 2025
  • 0 replies
  • 36 views

Forum|alt.badge.img

I have 3 Preventative Maintenance Actions on one object. On a new measurement the Plans have gone out of sync. 1 PM action shows the correct latest reading, 2400hrs. The other 2 have the previous reading 2100hrs. I tried regenerating the PM plans from all 3 PM and they remain out of sync. What causes the Out of Sync condition and how can this be fixed?