I am trying to connect a Repair Work Order to a superior work order which is connected to a project, i got below error message.
Same error message is also prompted when I am trying to connect the same Repair Work Order to the project using Project Connections. see below error.
Best answer by ereslk
Hi @ronhu.
Thanks for reaching out.
Do you have any reserved Material on the material lines? If there are already reserved quantities then it is not allowed for project connection until unreserved.
The working Quantity Assigned is misleading and totally agree with the confusion.
Do you have any reserved Material on the material lines? If there are already reserved quantities then it is not allowed for project connection until unreserved.
The working Quantity Assigned is misleading and totally agree with the confusion.
You are correct. I am connecting the repair work order to the project. as you might know, repair work is automatically reserved the repair object when it is intiated.