In the Maintenance Plan within Fleet and Asset Management, there are two calculation rules, Inspection and Overhaul, that works exactly the same way if the Cycle flag is set to No Cycle.

Does anyone currently have any maintenance plans where the combination of Calculation Rule = Overhaul and the Cycle flag = No Cycle?


2 replies

Userlevel 4
Badge +8

Hi @geirsigve,

Overhaul-The due date for this calculation rule, is based on the Value After Overhaul of the operational parameter of the serial. Every maintenance code with this calculation rule will repeat itself (after every cycle). Note: A maintenance code connected to this calculation rule must have either No Cycle or Cycle in the Cycle field. If a number of maintenance codes are used, the calculation rule with the highest interval must have the value Cycle in the Cycle field. Otherwise the calculation will not calculate the correct due dates for overhauls with longer intervals than the event controlling the cycle.

Observe that when you perform the maintenance code set as Cycle the Value After Overhaul and Value After Repair of all the serial's operational parameters will be reset.

Please use following link to learn how calculations are performed on each maintenance code connected to the maintenance plan determining calculation rules. 

http://docweb.corpnet.ifsworld.com/ifsdoc/Apps10/documentation/en/default.htm?openpage=http://docweb.corpnet.ifsworld.com/ifsdoc/Apps10/documentation/en/Vim/frmSerialStrTemplBasic.htm

Hope this will helps you.

Best Regards,

Bimsara

Userlevel 3
Badge +5

Thanks Bimsara for your reply.

 

However, I am aware of how the application works.  This was a question to the community to find out if anyone is in fact using that specific capability.  This because we  have a discussion on whether it should be removed from the application.