Hi @Phil Lamerton this one need to move to Asset Management
Hi @dadude ,
I followed below steps in 21R2 DEV CMB environment but, I could observe that work tasks are getting the status ‘Work Done’ once work assignments are completed.
- Create a work order in Prepare work order window with two tasks
- Assigned the tasks to a test user (alain)
- Release work tasks
- Go to Service Technician-My Assignments and accept the assigned tasks
- Go to ongoing assignments and complete each task while checking the work order from Prepare work order window
- Once a work assignment is completed each task was changed to “WorkDone” state in Prepare work order screen
Could you please let us know if you have followed a different test flow.
Thanks & Best regards,
Nethmini
Hi @dadude ,
Nothing has been changed around this behavior in 21R2.
As a general rule - when changing the last work assignment to Completed, the work task should go to Work Done (precisely as @Nethmini Kosvinna has observed when testing).
Hello,
I have also had this issue.
It seems to be intermittent, so I cannot peg the reason as to why/when it occurs.
WE do follow the process mentioned above
Is RMB Assign Multiple Tasks a factor since it does not link the the Resource Demand?
Thanks