We want to copy all the configuration from PROD to Preprod like resource creation,shift creation, skill,division etc. Please advise how to do this if anybody knows.
How to copy all the configuration from PROD to PREPROD
Best answer by Lee Pinchbeck
Hi
The first step would be to export the system parameters and ARP file (if in use) and then import these in to the preprod. This should cover most of the setup, if there is any other remaining setup that you need carried over that is not after these imports please advise us specifically of what needs to come over and we can advise the best way to do this.
Steps to export the system settings are:
System settings can be exported either via the Scheduling Workbench or via the installer.
In the PSO Workbench, go to any screen in the Administration workspace under the Organisation menu, and click on the ‘Administration’ button in the top right corner of the screen (visible if the user is an administrator) to open the ‘Import/Export’ options. Then click ‘Export Data’.
In the Silverlight Workbench, go to the ‘Import / Export’ screen in the Administration workspace, and click the ‘Export’ button.
See the installation guide for details of using the installer.
To obtain ARP:
ARP data can be exported either via the Scheduling Workbench or via the installer.
On the PSO Workbench, from any Planning workspace screen an ‘Administration’ button should be available in the top ribbon provided the user is an administrator. Click this to open the administration panel, and then click ‘Export’, ensuring that any rota data is included.
On the Silverlight Workbench, admin users can export data via the ‘Import / Export’ screen on the ‘Admin’ tab in the Planning workspace.
See the installation guide for details of using the installer.
Once you have the files go to the preprod and select inport instead of export at the relevant locations and select your exported files.
Kind regards,
Lee Pinchbeck