Hi all,

In IFS Cloud 21R1, I am looking for the required set up to make visible planned working time for a person resource in "Allocate resource" page.

From the legend, I can see color codes corresponding to Calendar Details so it should be possible to have them displayed

What I have done so far :

  • create a day type dependant schedule in HR and assign it to the employee with time base = generated results
  • the employee is linked to a resource with “use of HR schedule” activated
  • I executed 2 background jobs : Generate Timrep intervals and hours + Generate calendar for Gantt
  • I selected the option “Show working time” in the settings of the “Allocate resource” page

And yet I have a grey line throughout the day :

 

What am I missing ?

Is there anything else to do ?

 

Thanks for your help

Lénaïc

Best answer by janise

To get availability visible in 21R1 Gantt

I find to late that it got solved via Service, but below you get a short set up requirement…

1: Set up the resource and connect to a schedule…

2: In Gen Res, run the “Calculate Resource Capacity” for the resource.

3: Then set up a New Databas Task Schedule gor the Databas Task “Generate Calendars for Gantt”.

4: Run the Database Task Schedule

5: Check Background job and wait until ready

6: Hocus pocus and you will get the availability visible in the Gantts.

Regards,

//Janne

View original
Did this topic help you find an answer to your question?
This topic has been closed for comments

6 replies

Dilani
Hero (Employee)
Forum|alt.badge.img+4
  • Hero (Employee)
  • 22 replies
  • December 6, 2021

Hi Leniac,

In Aurena Gantt there is a minimum zoom in limit required to display work time. Try zooming in more. I think that could be the issue for having grey line throughout the day without showing work time.

Best Regards,
Dilani


LenaicDAVID
Hero (Employee)
Forum|alt.badge.img+14
  • Author
  • Hero (Employee)
  • 117 replies
  • December 6, 2021

Hi @Dilani 

Following your advice, I tried zooming in more and it did not change anything.

The line remains grey throughout the day.

Kind regards

Lénaïc


Dilani
Hero (Employee)
Forum|alt.badge.img+4
  • Hero (Employee)
  • 22 replies
  • December 6, 2021

Hi Leniac,

Ok that was a general guess related to Gantt. Sorry that didn’t helped. Since this is a functionality related to service I think you might get a quicker answer if moved there.

Best Regards,

Dilani


Forum|alt.badge.img+5
  • Do Gooder (Employee)
  • 46 replies
  • Answer
  • June 17, 2022

To get availability visible in 21R1 Gantt

I find to late that it got solved via Service, but below you get a short set up requirement…

1: Set up the resource and connect to a schedule…

2: In Gen Res, run the “Calculate Resource Capacity” for the resource.

3: Then set up a New Databas Task Schedule gor the Databas Task “Generate Calendars for Gantt”.

4: Run the Database Task Schedule

5: Check Background job and wait until ready

6: Hocus pocus and you will get the availability visible in the Gantts.

Regards,

//Janne


Forum|alt.badge.img+11
  • Sidekick (Customer)
  • 111 replies
  • November 8, 2022

hi

I did some settings in 

I added the shift in Resource shift calendar & I am able to see that in res shift gantt, also in dispatch console. But what is work time calendar & how is it related to res shift calendar, what happens when we generate it

 

 

Is there any document on calendar?

What is work day?


LenaicDAVID
Hero (Employee)
Forum|alt.badge.img+14
  • Author
  • Hero (Employee)
  • 117 replies
  • November 10, 2022

Hi @anushakh 

The question in my post was referring to resource availability coming from HR schedule and not from Resource shift. These are 2 different ways to set up resource availability.

i would advise you to create a new post on the Community to ask your question.

Kind regards

Lénaïc