Work Assignment Actual Hours Worked


Forum|alt.badge.img+11

When an Engineer creates work via the Service Engr MWO App, if they create ‘New Work’ using the option ‘Report Work I have Done’ when the Work Order is returned from MWO the Actual Hours Worked displays in the Work Assignment but it does not generate a Time Report for that User.

 

Without a Time Report there is no Cost Line and without a Cost Line we have no Sales Line.

Is it correct that the Time Report is not automatically created? How do we get the system to create a Time Report? Does this need to be manually done?

 

Thanks in advance

Best answer by James Ashmore

The concept today is to do this reporting manually. I like the idea of automatically creating this tough so could you please add this as an Idea

Cheers

James

View original
Did this topic help you find an answer to your question?

2 replies

James Ashmore
Hero (Employee)
Forum|alt.badge.img+16
  • Hero (Employee)
  • 472 replies
  • Answer
  • March 13, 2023

The concept today is to do this reporting manually. I like the idea of automatically creating this tough so could you please add this as an Idea

Cheers

James


Forum|alt.badge.img+11
  • Author
  • Sidekick (Customer)
  • 99 replies
  • March 13, 2023

Thanks for the reply James, I have created this as an Idea and will ensure the Team know to report manually moving forward.