Skip to main content
Question

Which posting control I am missing for project time reporting

  • September 11, 2022
  • 1 reply
  • 109 views

Forum|alt.badge.img+16

Community, 

 

wondering which posting control I am missing for report project resource time. please refer to the screenshot. 

i have reported the hours against the project using correct report code, but there is no Reported Hours reported to the project. not sure which posting type i am missing to set up. 

Thank you.

1 reply

Forum|alt.badge.img+28
  • Superhero (Customer)
  • September 12, 2022

Look at PRJT1 and PRJT2 first.