Hi,
We are interested in using the planned purchase cost in cost set 5.
It works good for entities that don’t have Part Step Pricing in their Supplier agreements or Supplier for Purchase part Price lists. We are on ifs10
I have understood that when calculating planned purchase cost in this cost set, system will use purchase pricing logic, similar to when you enter a purchase order line for a part no.
I also read in another tread that when calculating the planned purchase cost in Costing system will use:
- the standard lot size as order qty
- the effectivity date as price date.
For some reason we do not get this to work when using price breaks, even if we have the standard lot size on the inventory part.
Any one that have any input that could help us?
Regards,
Marika