Question

Discrepancy Between Customer Schedule Forecast and MS

  • September 17, 2020
  • 1 reply
  • 212 views

ctaylor56
Hero (Partner)
Forum|alt.badge.img+14

We’re importing Customer Schedule Forecasts into Master Scheduling.  It’s working but I have a discrepancy I can’t account for.

 

Customer Schedule Lines show a forecast between  2 customers for a total of 3456

 

 

Master Scheduling MS Level 1 Part shows a total forecast qty of 3434

 

 

Any ideas why these would differ?

1 reply

Forum|alt.badge.img+14
  • Hero (Employee)
  • 291 replies
  • September 20, 2020

Hello!

It would be useful if you provide a screenshot of the Import Customer Schedules dialog box - which parameters you are using. Right now I don’t have a clue, but please check your Customer Schedule demands that are close to the Demand Timefence threshold. For the part you provided I saw it was 9/23. Customer Schedule demands at 9/24 and later will be imported. (of course this threshold will slide as the days goes by...) Anyway, that could at least be something to start with for your investigation.

 