Supplier for Purchase Part Lead Times on supplier for Purchase Part

  • February 14, 2022
  • 2 replies
  • 413 views

Mdangelo
Sidekick (Customer)
Forum|alt.badge.img+8

We would like to confirm the rules for Supplier for Purchase Part Lead Times on General Tab on the Supplier for Purchase Part.

We were told that the Procurement Lead Times are on a 7 day/week calendar and that all other lead times in IFS are based on a 5 day/week calendar.

Example: Supplier Lead Time = 4 weeks. 4x7=28 days lead time

Manufacturing or Expected Lead Times = 4 weeks. 4/20

Can someone please help us confirm?

Thank you,

Michelle

Best answer by Mdangelo

Yes, great. This is how I understood it. Thank you for the clarification as well.

View original
Did this topic help you find an answer to your question?
This topic has been closed for comments

2 replies

Forum|alt.badge.img+28
  • Superhero (Customer)
  • 1482 replies
  • February 14, 2022

Your summary is close.

Supplier Lead Time on the SfPP is at 7 days

Purchasing Lead Time on the Inventory Part is at 7 days

Manufacturing Lead Time on the Inventory Part is at 5 days

Expected Lead Time is derived based on the Part Type that the Inventory Part is currently set to for that level item, which may be Purchased or Manufactured.  So the Expected Lead Time (ELT) can be either 5 or 7 depending on the current Inventory Part setting.  ELT will update automatically when you change the Purchasing or Manufacturing Lead Time, but also can be set independently of both of those values.


Mdangelo
Sidekick (Customer)
Forum|alt.badge.img+8
  • Author
  • Sidekick (Customer)
  • 20 replies
  • Answer
  • February 14, 2022

Yes, great. This is how I understood it. Thank you for the clarification as well.