Hi,
I tried to find an answer on previous topics but i’m afraid my use case is not covered.
I’d like to implement the below functionning in IFS :
- If I have a need of 10 PCS for component A (customer order)
- And if I already have 8 PCS of component B in stock.
- I want a need of only 2 PCS of component A to be triggered by the system (purchase requisition).
To do so i guess i need to set-up part B as alternate of part A.
I tried to set-up alternate purchase part & alternate component functionalities but it does not seems to work, even when “Include in MRP netting” is set-up at alternate component level, and when “plan alternate component” is ticked for MRP performing.
I guess I missed a piece of set-up.
Thanks for your precious help.
BR.
Baptiste.
Note : I’m on IFS cloud 21R1.
Question
Alternate part functionalities for purchasing and planning