Connecting a control plan for pegged shop order


RajanKhatri7
Sidekick (Customer)
Forum|alt.badge.img+8

Hello,

 

I am trying to connect a control plan for a shop order which is pegged from customer order. IFS is showing me an error that “Cannot connect control plan to this shop order” . Is it a bug or standard functionality ? 

 

We need our QA team to inspect and enter analysis for customer orders created to address quality issues.

 

Please let me know.

 

Thank you.

 

Best answer by Peter Lundgren

If a valid control plan manufacturing revision exists for the part of interest, then it should be connected to the shop order automatically when the shop order is created, regardless if the shop order is pegged to a customer order or not.

The control plan revision is valid if the status is Active, and the shop order need date falls within the date range defined by the control plan revision Phase In and Phase Out dates.

View original
Did this topic help you find an answer to your question?

2 replies

Peter Lundgren
Hero (Employee)
Forum|alt.badge.img+7
  • Hero (Employee)
  • 61 replies
  • Answer
  • April 26, 2022

If a valid control plan manufacturing revision exists for the part of interest, then it should be connected to the shop order automatically when the shop order is created, regardless if the shop order is pegged to a customer order or not.

The control plan revision is valid if the status is Active, and the shop order need date falls within the date range defined by the control plan revision Phase In and Phase Out dates.


RajanKhatri7
Sidekick (Customer)
Forum|alt.badge.img+8
  • Author
  • Sidekick (Customer)
  • 57 replies
  • April 27, 2022
Peter Lundgren wrote:

If a valid control plan manufacturing revision exists for the part of interest, then it should be connected to the shop order automatically when the shop order is created, regardless if the shop order is pegged to a customer order or not.

The control plan revision is valid if the status is Active, and the shop order need date falls within the date range defined by the control plan revision Phase In and Phase Out dates.

Hi Peter,

Thank you for the response. Your explanation resolved my issue as I didn't check the phase in date of control plan and finish date of the shop order. After adjusting the dates, I was able to connect and use it .


Reply