Hello,
I’m attempting to use the Copy Part feature to copy an Inventory Part, Routing, and Product structure to another site in my system. Currently, we are creating parts in an estimating site that houses all of our work centers, labor classes, etc. Once the parts are finalized, I would like to use the Copy Part function to move those parts to the correct manufacturing site.
I have noticed that the Copy Part function works, however it does not bring over my routing steps. I’ve tried changing the status to Build, but the routing steps still do not appear after the copy. I’m not sure if there is something I’m missing, or if this is how the Copy Part function works when you try to copy to another site.
The final item I’ve noticed is that you are not able to copy a new Product Structure component part to a new site unless you manually copy the part prior to running the Copy Part from the top level Inventory Part. My assumption was that if you run the Copy Part from the top level, if there are any new component parts in the Product Structure that do not currently exist in the new site, those would simply be copied over when you initiated the Copy Part from the top level part. Is this not the case, and you in fact must manually copy over every single new component part before attempting the top level part copy?
Thank you