Hello

I want to get the right holiday wage code in the time card result tab based on the normal working hours that are in an employee std. schedule.

So I set up a Public holiday compensation schedule with a calculated result based on the std. wage code that day.

When I look in the schedule of that day I can see that the PHC day type is filled in according to the holiday schedule.

The problem is that according to the online help the code should appear in the result tab but it doesn’t appear…

 

Kind regards

David

Best answer by Shehan Almeida

Hi David,

 

Have you tried to execute the back ground job ‘Generate TimRep Intervals’ 

 

 

That is how the PHC is suppose to generate results.

Hope this helps.

 

Shehan Almeida.

 

View original
Did this topic help you find an answer to your question?
This topic has been closed for comments

6 replies

Shehan Almeida
Superhero (Partner)
Forum|alt.badge.img+18
  • Superhero (Partner)
  • 270 replies
  • Answer
  • January 12, 2021

Hi David,

 

Have you tried to execute the back ground job ‘Generate TimRep Intervals’ 

 

 

That is how the PHC is suppose to generate results.

Hope this helps.

 

Shehan Almeida.

 


Forum|alt.badge.img+5
  • Author
  • Do Gooder (Customer)
  • 16 replies
  • January 20, 2021

Hi Shehan

 

That works, thx! But the problem I have now is that we already get holiday requests f.e. the week between Christmas and New Years. 

So we will confirm these days already but can’t confirm the holidays because the job will only calculate the past days.

Is there a solution for this?

 

David


Shehan Almeida
Superhero (Partner)
Forum|alt.badge.img+18
  • Superhero (Partner)
  • 270 replies
  • January 20, 2021

Hi David,

 

Your new issue is not clear. 

If the days are not confirmed the PHC will calculate for past days as well. Hope this helps.

 

Shehan Almeida.

 


Forum|alt.badge.img+5
  • Author
  • Do Gooder (Customer)
  • 16 replies
  • January 20, 2021

Hi Shahan

 

When you run the PHC today it will only calculate the past 14 days but will not yet calculate the Public holidays that I already entered for christmas this year. 

I’m searching for a solution that will also calculate future dates so we can already confirm them.

 

David


Shehan Almeida
Superhero (Partner)
Forum|alt.badge.img+18
  • Superhero (Partner)
  • 270 replies
  • January 20, 2021

Hi David,

 

Application is designed to generate time for the past time based on the schedules. I believe you will need modification for your requirement.

 

Shehan Almeida. 


Forum|alt.badge.img+5
  • Author
  • Do Gooder (Customer)
  • 16 replies
  • January 21, 2021

Thx for the info Shehan!


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings