Question

Project transactions - cost base mark up not pupulated

  • September 13, 2024
  • 1 reply
  • 36 views

Nipuni.J
Do Gooder (Partner)
Forum|alt.badge.img+5

Hi, 

I have a cost base mark up % defined in the project specific sales pricing for a specific report code (Expense). When I create an expense sheet for the activity, confirm and authorize it creates a project transaction but mark up is does not pupulate. 

if I edit the same project transaction and change the internal price, the mark up is populated. 

Has anyone encountered this? Is there a fix for this? 

 

Thank you. 

1 reply

Forum|alt.badge.img+9

Hi @Nipuni.J ,

The Cost Plus margin functionality is not supported for travel expenses, and instead there is separate functionality to handle this requirement.

Please have a look at the ‘Margin for Travel Expense’ section in the Navigator:


There is some additional information about this in the documentation, e.g. here:

https://docs.ifs.com/ifsclouddocs/24r1/ProjectReporting/ActivityRegTravExpMargin.htm?StandAlone=true

Hope this helps.

Kind regards,
Johan

 


Reply